Nigerian govt extends reopening of Third Mainland Bridge
Spread the love

Hits: 11

The Federal government has reported that the Third Mainland Bridge will at this point don’t be opened on Monday however toward the finish of February.

The Federal Controller of Works in Lagos, Mr Olukayode Popoola who made this known to newsmen said that the extension would be closed down again from Feb. 19 to 21 for culmination of the undertaking.

Popoola uncovered that it was unimaginable for the worker for hire to close the Bridge during the week to project concrete.

He said the scaffold will, be that as it may, be resumed before the finish of February.

“Third Mainland Bridge will no longer be opened on the 15th of February 2021 as announced earlier.

“This decision was taken in order not to create hardship for the motoring public using the Third Mainland Bridge for their daily activities.

“We are looking at the end of the month for the reopening of the bridge. That is, end of this February.

“They will cast concrete on the last expansion joint next weekend and this cannot be done during the week because we are trying to endure that there will not be so much traffic for people going about their daily activities.

“When this casting is done, we need about three or four days to do post tensioning. That is why we are looking at end of February completion.

“Casting will be done next weekend for the last expansion joint and this will require total closure of the bridge.

“However, if we close the bridge Friday night, then we cast on Saturday by Sunday it will be reopened. That will be the last total closure to fix the last expansion joint.

“We also regret the inconveniences these extra days will cause Lagosians,’’ he said.